INGURHES HAS RESUMED ITS WORK

Wednesday, 28 April 2021 12:10 368

Sukhum. April 27, 2021. Apsnypress. The Ingur hydroelectric power station has resumed its work today, after repairs completion in the diversion tunnel.

The station was launched ahead of schedule. The current restriction schedule has been canceled. During the week, the power system of the republic will operate in test mode. Minor power outages are possible during this time.

Ingur HES was shut down on January 20 for repairs in the diversion tunnel.

The diversion tunnel itself is 9.5 meters in diameter and 15.5 km long. Repair work was carried out according to the plan in the most problematic areas with the highest water losses. Their total length was about three kilometers. In total, from 250 to 280 million kilowatt-hours were lost per year due to water leaks in the diversion tunnel.

The repair work was carried out in three shifts, 22 hours a day.